Project Description
Bondi Wastewater Treatment Plant
Thompson Controls was engaged as a contractor by Sydney Water for this ongoing project, as part of the SMART team.
The Bondi WWTP ocean outfall effluent pump panel required replacement due to a number of factors including:
- Ageing
- Unmaintainable components
- Previous fire incidents
- Dangerous busbars
- Damage to cables from hydrogen sulphide in the air.
The Thompson Controls’ team undertook design, supply, installation and commissioning work, including:
- Remove existing high voltage cables
- Install new high voltage cables for existing high head pumps
- Create space within SWR610 to allow for the installation and cut over of replacement SCA
- Consolidate HV pump monitoring and controlling I/O onto Modbus networks
- Consolidate field I/O associated with existing DCS into new ELP and PLP panels
- Decommission existing EP panels to create space for new SCA’s
- Consolidate essential services starters and power distribution into separate SCA
- Construct and install new PLP’s and UPP’s.
- Undertake Profibus, Modus and Foundation Fieldbus interfaces to existing equipment and networks
- Modify existing control power distribution system (UPP’s)
- Install of new fibre optics network
- Install Ethernet SCADA and Control network
Project Details
Business unit: Electrical Controls & DesignClient: Sydney Water
Current status: Complete
Start date: Nov 2016
Completion period: Ongoing
Contract type: $1.6 Million
Value: N/A